In a fixed time and budget project, the customer wants the development of a core component to be based on agile practices, as the final
In a fixed time and budget project, the customer wants the development of a core component to be based on agile practices, as the final scope of the requirement has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact the profitability of the project. Which two controls should the project manager incorporate into the contract to specifically address the development of the core: component? (Choose 2) Tier the contract for fixed and agile components. Limit the number of iterations for development in the contract: Require that only internal resources be utilized for this project Establish a governance committee to review the contract delivery. Provide alternatives to scope change at specific project phases within the contract
Step by Step Solution
There are 3 Steps involved in it
Step: 1
1 Tier the Contract for Fixed and Agile Components Explanation Tiering the contract involves separating the project into distinct parts that are managed differently Fixed Components These are welldefi...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started