In a project where an unplanned and unidentified event occurred in the risk registers, the project manager implemented a temporary solution for the event. What
In a project where an unplanned and unidentified event occurred in the risk registers, the project manager implemented a temporary solution for the event. What should be done next? Select the correct answer Report budget and schedule changes. Plan a definitive response. Identify the root causes of the risk and assess them. Use the management reserve