In a project you have 3 alternatives with the following costs: Complete inhouse: The initial cost is 50.000 . A full-time engineer will be

 

In a project you have 3 alternatives with the following costs: Complete inhouse: The initial cost is 50.000 . A full-time engineer will be hired at an annual wage of 26.000 . Cost of production is 10 per product. Partial inhouse: Partial equipment has an initial cost of 35.000 . A part-time engineer has a wage of 10.000 . Due to partial outsourcing the production cost is 43 per product. Outsourcing: You don't have initial cost and you don't hire any engineer. You outsource all production and the cost is 120 per product. This project has a life of 6 years. If MARR is 10% determine the number of products that should be produced each year to justify: a) the complete inhouse b) the partial inhouse c) If you plan to produce 300 products, which method is the best economically?

Step by Step Solution

3.44 Rating (170 Votes )

There are 3 Steps involved in it

Step: 1

To determine the number of products that should be produced each year to justify each alternative complete inhouse partial inhouse and outsourcing we ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting

Authors: Kin Lo, George Fisher

3rd Edition Vol. 1

133865940, 133865943, 978-7300071374

More Books

Students also viewed these Economics questions

Question

List the characteristics of wellset goals.

Answered: 1 week ago

Question

How does an ERP system differ from MRP II software?

Answered: 1 week ago