In a qualitative risk assessment, you consider the possibility of a coolant failure affecting a $ 5 million piece of research equipment. You had calculated
In a qualitative risk assessment, you consider the possibility of a coolant failure affecting a $ million piece of research equipment. You had calculated that the threat would destroy the asset, but on further review, it would only be a $ million repair. What value should you change in the assessment formula? Choose the best response.
a
SLE
b
ALE
c
AV
d
EF
e
ARO