In a resource-constrained project the second priority in assigning resources is usually given to activities with Select one: a. smallest duration. b. highest cost. c.
In a resource-constrained project the second priority in assigning resources is usually given to activities with
Select one:
a. smallest duration.
b. highest cost.
c. lowest identification number.
d. least slack.
E. mosts lack