In a safety stock problem where both demand and lead time are variable, demand averages 100 units per day with a daily standard deviation of
In a safety stock problem where both demand and lead time are variable, demand averages 100 units per day with a daily standard deviation of 10, and lead time averages 28 days with a standard deviation of 2 days. What should the (approximate) reorder point be for a 95% service level? (Do not round intermediate calculations. Round answer to the nearest whole number.)
OA. 340 units
OB. 4,445 units
OC. 2,817 units
OD. 2,997 units
OE. 3,140 units