Question

1 Approved Answer

In a safety stock problem where both demand and lead time are variable, demand averages 100 units per day with a daily standard deviation of

In a safety stock problem where both demand and lead time are variable, demand averages 100 units per day with a daily standard deviation of 10, and lead time averages 28 days with a standard deviation of 2 days. What should the (approximate) reorder point be for a 95% service level? (Do not round intermediate calculations. Round answer to the nearest whole number.)
OA. 340 units
OB. 4,445 units
OC. 2,817 units
OD. 2,997 units
OE. 3,140 units
image text in transcribed
In a safety stock problem where both demand and lead time are variable, demand averages 100 units per day with a daily standard deviation of 10 , and lead time averages 28 days with a standard deviation of 2 days. What should the (approximate) reorder point be for a 95% service level? (Do not round intermediate calculations. Round answer to the nearest whole number.) A. 340 units B. 4,445 units C. 2,817 units D. 2,997 units E. 3,140 units

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

470533013, 978-0470533017

More Books

Students also viewed these General Management questions