In an industrial project the equipment installation can be started 1 5 days after the equipment foundation is completed. What type of dependency is this?

In an industrial project the equipment installation can be started 15 days after the equipment foundation is completed. What type of dependency is this?
Question 12 options:
Start-to-finish with a 15-day lead
Finish-to-finish with a 15-day lag
Finish-to-start with a 15-day lag

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding And Managing Public Organizations

Authors: Hal G. Rainey

4th Edition

047040292X, 978-0470402924

More Books

Students also viewed these General Management questions

Question

1. Make sure you can defend the grade in the first place.

Answered: 1 week ago

Question

1. Outline the listening process and styles of listening

Answered: 1 week ago

Question

4. Explain key barriers to competent intercultural communication

Answered: 1 week ago