Question

1 Approved Answer

In any of construction project, constraining resources implies that the project duration will be extended. However, leveling resources has the connotation that the project duration

 

In any of construction project, constraining resources implies that the project duration will be extended. However, leveling resources has the connotation that the project duration will remain the same and most of resource leveling techniques assume that activities cannot be split.

Resource leveling also aims at minimizing resource usage fluctuations, which is accomplished by moving noncritical activities within their float. By using an example of the simple construction project with at least five activities, develop a resource leveling chart and discuss it appropriately.


Step by Step Solution

3.39 Rating (158 Votes )

There are 3 Steps involved in it

Step: 1

Resource leveling is a technique in project management that involves adjusting the project schedule to ensure that resources are used efficiently and ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Accounting

Authors: Susan S. Hamlen, Ronald J. Huefner, James A. Largay III

2nd edition

1934319309, 978-1934319307

More Books

Students also viewed these General Management questions

Question

Describe six danger signs of a bust-out artist.

Answered: 1 week ago