In determining Critical Path, a Project Manager would consider . . . Question 7 options: A . the longest path in the overall network diagram.
In determining Critical Path, a Project Manager would consider
Question options:
A the longest path in the overall network diagram.
B those tasks with the highest associated risk.
C identify which tasks have the least amount of slack.
A and C only.
All the above.