In February 2 0 2 3 , Crane Construction signed a contract and commenced construction on a parking garage. The total contract price was $
In February Crane Construction signed a contract and commenced construction on a parking garage.
The total contract price was $ million and was expected to be completed in July at a total estimated cost of $ million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. Based on the terms of the contract with the customer, control over the parking garage ie ownership does not transfer to the customer until completion. Crane's yearend was September and follows ASPE.
By the end of September, Crane had incurred $ in costs and had invoiced $ in progress billings. $ of the progress billings had been collected.
By September Crane had incurred $ in total costs and had invoiced $ in progress billings, including the progress billings in Of the total billings, $ had been collected. Also, Crane reviewed its cost estimates on the project, and now believed the parking garage would cost $ million in total to complete.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started