Question
In January 2014, XYZ Inc. began construction on a commercial building for Firm ABC which had a contract price of $2,900,000. The construction is scheduled
In January 2014, XYZ Inc. began construction on a commercial building for Firm ABC which had a contract price of $2,900,000. The construction is scheduled to be completed in April 2016.
Contract information for all three years is given below at the companys December 31 year-end.
| 2014 | 2015 | 2016 |
Contract costs incurred during the year | 400,000 | 1,700,000 | 600,000 |
Estimated additional costs to complete | 2,300,000 | 400,000 | - |
Billings to Firm ABC during the year | 350,000 | 1,650,000 | 900,000 |
Cash collection during year | 325,000 | 1,550,000 | 1,025,000 |
Using the percentage-of-completion method, fill in the incomplete journal entries for XYZ Inc. Make sure your final answer(s) are accurate to the nearest whole number.
2014 | 2015 | 2016 | |||||
Date | Account | Debit | Credit | Debit | Credit | Debit | Credit |
Dec 2014 to 2016 | Construction in progress | ??? | ??? | ??? | |||
Cash, materials, etc | ??? | ??? | ??? | ||||
Dec 2014 to 2016 | Accounts receivable | ??? | ??? | ??? | |||
Billings on constructions contract | ??? | ??? | ??? | ||||
Cash | ??? | ??? | ??? | ||||
Accounts receivable | ??? | ??? | ??? | ||||
Dec 2014 to 2016 | Construction expense | ??? | ??? | ??? | |||
Construction in progress (gross profit) | ??? | ??? | ??? | ||||
Revenue from long-term contracts | ??? | ??? | ??? | ||||
Dec 2014 to 2016 | Billings on construction contract | ??? | |||||
Construction in progress | ??? |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started