in Microsoft Project Resource Graph display, one can change the time axis to show weeks or months. During analysis of a project, the peak units
in Microsoft Project "Resource Graph" display, one can change the time axis to show weeks or months. During analysis of a project, the peak units appeared as 5 in each of the four successive weeks in a particular month for a resource. If the time axis for the graph is changed to show months for that resource, the peak units for that month will appear as 20. True False