Question
1 Approved Answer
In month 9 the following project information is available: actual cost is $ 2 , 0 0 0 , earned value is $ 2 ,
In month the following project information is available: actual cost is $ earned value is $ and planned cost is $ Compute the SV for the project. Enter your answer as a positive or negative number without the dollar sign.