Question

1 Approved Answer

In month 9 the following project information is available: actual cost is $2,000, earned value is 1,917, and planned cost is 2,086. Compute the CV

In month 9 the following project information is available: actual cost is $2,000, earned value is 1,917, and planned cost is 2,086. Compute the CV for the project.

In month 9 the following project information is available: actual cost is $2,000, earned value is 1,924, and planned cost is 2,397. Compute the SV for the project.

On day 51 a project has an earned value of 582, an actual cost of 645, and a planned cost of 540. Compute the CPI for the project. On day 51 a project has an earned value of 600, an actual cost of 631, and a planned cost of 580. Compute the SPI for the project.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Asset Management A Systematic Approach To Factor Investing

Authors: Andrew Ang

1st Edition

0199959323, 978-0199959327

More Books

Students also viewed these General Management questions

Question

Where do attitudes come from? How do they change?

Answered: 1 week ago

Question

a score of 60 or higher on the test?

Answered: 1 week ago