In month 9, the following project information is available: Actual cost is $2,200 Earned value is $1,800 Planned cost is $2,200. Compute the CV and

In month 9, the following project information is available:

Actual cost is $2,200

Earned value is $1,800

Planned cost is $2,200.

Compute the CV and SV for the project.