In MRP planning, which of the following statements concerning safety stock is not accurate? Multiple Choice Safety stock is required only for end items, not
In MRP planning, which of the following statements concerning safety stock is not accurate?
Multiple Choice
- Safety stock is required only for end items, not for parts and subassemblies.
- Variability in lead times and scrap rates are two reasons safety stock is required.
- Planned order releases can be increased by a percentage equal to the expected scrap rate.
Safety time instead of safety stock is used when lead times are variable.