. In Oman Machine Manufacturing company, following 8 jobs are waiting to be processed. All the six jobs were logged as they arrived. All dates
. In Oman Machine Manufacturing company, following 8jobs are waiting to be processed. All the six jobs were logged as they arrived. All dates are specified as planning calendar days. Assume that todays date is 23.
Job | Due Date | Remaining Time (days |
A | 28 | 7 |
B | 25 | 5 |
C | 29 | 7 |
D | 26 | 6 |
E | 28 | 4 |
F | 27 | 6 |
G | 26 | 5 |
H | 28 | 6 |
Using the critical ratio scheduling rule, in what sequence would the jobs to process?