In order to implement a project, the WBS must be converted into an operating timetable otherwise known as a_________________. A. Network Diagram B. Critical Path
In order to implement a project, the WBS must be converted into an operating timetable otherwise known as a_________________.
A. | Network Diagram | |
B. | Critical Path | |
C. | Project Schedule | |
D. | Microsoft Project |