In order to track the progress of a rehabilitation project, Jane was creating a PERT. She enumerated the pursuits A through F. Activities E and
In order to track the progress of a rehabilitation project, Jane was creating a PERT. She enumerated the pursuits A through F. Activities E and F are the immediate predecessors of Activity D. The final activities were E and F. The earliest finish times for E and F were E-22 and F-18. What time does activity D have to be completed by the earliest?