Question:
) In performing bottom-up estimating, you take each activity in a work package and, in calculating the costs for that activity, take into consideration which of the following? Choose two.
Materials required
Work effort duration
Hourly or daily rate
Sick leave and vacation time
Paid holidays
2) From the list below, select the most precise form of project cost estimation.
Analogous
Top-down
Parametric
Bottom-up
Expert judgment
3) In which process is the majority of the project budget spent?
Initiating
Planning
Executing
Controlling
Closing
4) How is burn rate typically calculated?
CV
CPI
CPR
AC-PV
5) You'll use analogous estimating in the final stages of creating your project budget. (True / False)
True
False