Answered step by step
Verified Expert Solution
Question
1 Approved Answer
In preparing the MRP example Phil planned to use the worksheets shown and to make the following assumptions: 1. Seventeen gear boxes are on hand
In preparing the MRP example Phil planned to use the worksheets shown and to make the following assumptions: 1. Seventeen gear boxes are on hand at the beginning of Week 1, and six gear boxes are currently on order to be delivered at the start of Week 2. 2. Forty six input shafts are on hand at the start of Week 1, and 18 are scheduled for delivery at the beginning of Week 2 Model 1000 master schedule Week 2 3 4 5 6 7 8 9 10 11 12 Demand 13 6 10 18 24 14 2 15 Model 1000 product structure Engine assembly Gear box Crankcase Lead time = 2 weeks Used: 1 per engine Input shaft Lead time = 3 weeks Used 2 per gear box a. Initially. assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot (L4L). (Leave no cells blank - be certain to enter "O" wherever required.) Gear Box Requirements Week: 1 2 3 4 5 7 8 9 10 11 12 Gross requirements 13 6 8 10 0 18 24 14 0 2 15 Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order releaseInput Shaft Requirements Week: 2 3 4 5 6 7 10 11 12 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order release Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. These costs are as follows: PART COST Gear Box Setup = $120/order Inventory carrying cost = $2/unit/week Input Shaft Setup = $60/order Inventory carrying cost = $1/unit/week Suppose least-total-cost lot sizing is to be used. Using the planned order receipts shown below, complete the remainder of the gear box and input shaft tables. (Leave no cells blank - be certain to enter "0" wherever required.) Gear Box Requirements Week: 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements 13 6 10 0 8 24 14 0 8/ 2/ 15 Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order release Input Shaft Requirements Week: 2 3 4 7 10 11 12 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipt 82 0 50 Planned order releasec. What are the savings with the new schedule? Assume inventory is valued at the end of each week. Cost of the schedule from part (a) Setup Cost Inventory Total Gear box Input shaft Total cost Cost of the schedule using least-total-cost lot sizing. Setup Cost Inventory Total Gear box Input shaft Total cost Savings with the new schedule. Savings
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started