In project schedule management, the main goal of which process is to ensure that the project team has complete understanding of all the work they
In project schedule management, the main goal of which process is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work?
a
estimating activity resources
b
estimating activity durations
c
controlling the schedule
d
defining activities