In the context of closing out a construction project, a significant document is the Certificate of Substantial Completion. What is the appropriate timing for the
In the context of closing out a construction project, a significant document is the "Certificate of Substantial Completion. What is the appropriate timing for the issuance of this document in the project's closing process? A The contractor's Punch-List completed and approved by the Architect B) After the "preliminary" Punch-List is completed ( C) When the owner agrees to the Punch list D When Architect prepares Contractor's Punch-List