In the context of project selection, when the discount rate is decreased, A . there is no change in the present value. B . net
In the context of project selection, when the discount
rate is decreased,
A there is no change in the present value.
B net present value would equal zero.
C the present value of future cash flows increases.
D the present value of future cash flows decreases.