In the design phase, a consulting fee paid to a third party affects which of the following project profitability metrics: 1. lowers the NPV 2.
In the design phase, a consulting fee paid to a third party affects which of the following project profitability metrics:
1. lowers the NPV
2. none of them, since the fee is a "sunk cost" that must be paid regardless of whether the project is built
3. raises the ROI substantially
4. shortens the Payback Period