In the middle of a software development project, the lead design programmer accepted an offer from a competitor. The project manager needs to find a
In the middle of a software development project, the lead design programmer accepted an offer from a competitor. The project manager needs to find a replacement to meet an upcoming What should the project manager do? Consult the risk response plan. Update the resource calendar. Issue a request to the change control board (CCB). Assign the tasks to another team member