In the t = ( a + 4 m + b ) / 6 calculation for expected activity completion time, the a refers to ?

In the t =(a +4m + b)/6 calculation for expected activity completion time, the a refers to?
Group of answer choices
Activity completion time variance
Pessimistic completion time
Most likely completion time
Optimistic completion time

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Applied Wildlife Habitat Management

Authors: Roel R. Lopez, Michael L. Morrison, Israel D. Parker

1st Edition

9781623495022

More Books

Students also viewed these General Management questions

Question

16. Use Exercise 15 to show that P(E F) = P(E) + P(F) P(EF).

Answered: 1 week ago

Question

Explain the factors influencing wage and salary administration.

Answered: 1 week ago

Question

Examine various types of executive compensation plans.

Answered: 1 week ago

Question

1. What is the meaning and definition of banks ?

Answered: 1 week ago