In the table below, a general complex flow problem where 3 jobs are processed on 3 machines is given. Calculate the maximum completion time and
In the table below, a general complex flow problem where 3 jobs are processed on 3 machines is given. Calculate the maximum completion time and the percentage of use of each machine by producing a lag-free schedule for this problem. (When it is time to start equal, priority will be given to Job 1 between Jobs and SPT between Actions)
operation (machine, operation time) work 1 2 (C,12) (0,5) (C,4) (A,4) (C, 11) (D,1) 3 (B,3) (A,3) (A,7) 2 3 operation (machine, operation time) work 1 2 (C,12) (0,5) (C,4) (A,4) (C, 11) (D,1) 3 (B,3) (A,3) (A,7) 2 3Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started