Question
In this example, the control account manager (CAM) statuses work package 8 as of end of November. Given the Earned Value Management (EVM) technique for
In this example, the control account manager (CAM) statuses work package 8 as of end of November. Given the Earned Value Management (EVM) technique for this work package, what is the BCWP for the month of November? Excerpt of the Engine Critical Design CAP. Work package 8 Engineering Support uses an LOE EVM technique with BCWS scheduled as follows: August $6,983; September 8,938; October 8,938; November $9,760; and December $8,938. The BAC is $43,557. Time Now is at the end of November. The current BCWS for each month is: August $6,983; September 8,938; October 8,938; November $9,760; and December $8,938. The current BCWP for each month is blank.
possible answers
$34,619 |
$0 |
$9,760 |
$18,698 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started