In your project, you have used valuable inputs to produce project activity metrics to evaluate actual progress as compared to planned progress. The inputs used
In your project, you have used valuable inputs to produce project activity metrics to evaluate actual progress as compared to planned progress. The inputs used during the Control Quality process are:
A. Risk register B. Organizational process assets C. Quality management plan D. Work performance data
a) B,CandD b) A,CandD c) A,BandD d) A,BandC