Indiana Co. began a construction project in 2016 with a contract price of $162 million to be received when the project is completed in 2018.

Indiana Co. began a construction project in 2016 with a contract price of $162 million to be received when the project is completed in 2018. During 2016, Indiana incurred $33 million of costs and estimates an additional $82 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed.

In 2017, Indiana incurred additional costs of $59 million and estimated an additional $39 million in costs to complete the project. Indiana (Do not round your percentage calculated):

Recognized $8.28 million gross profit on the project in 2017.

Recognized $7.00 million gross profit on the project in 2017.

Recognized $29.50 million gross profit on the project in 2017.

Recognized $31.00 million gross profit on the project in 2017.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions