Information for 22 to 26. In 2012 Norcraft Sisters Construction agreed to construct a residence hall at University of Houston at a price of $1,200,000.
Information for 22 to 26. In 2012 Norcraft Sisters Construction agreed to construct a residence hall at University of Houston at a price of $1,200,000. The information relating to the costs and billings for this contract is shown below. 2012 2013 2014 Costs incurred during the year $ 280,000 $320,000 $850,000 Estimated costs to complete 520,000 300,000 –0– Customer billings to date 300,000 400,000 850,000 Collection of billings to date 200,000 320,000 800,000
22. Assuming that the percentage-of-completion method is used, compute the amount of gross profit (loss) to be recognized on income statement in 2012 and 2013, respectively
a. $400,000 and 300,000.
b. $140,000 and 60,000.
c. $140,000 and 200,000.
d. $0 and $0.
23. Assuming that the percentage-of-completion method is used, which of the following is reported on the balance sheet at Dec. 31, 2012?
a. Receivable under current assets with a balance of $420,000
b. Net of Construction in Progress and Billings on C.I.P under current assets with a balance of $120,000
c. Billings on C.I.P under current liabilities with a balance of $300,000
d. Construction in Progress under current liabilities with a balance of $280,000
24. Assuming that the percentage-of-completion method is used, what is the amount of Revenue from Long-Term Contracts and Construction Expenses recognized for the year 2013? Revenue Expenses
a. $800,000 $320,000
b. $380,000 $ 320,000
c. $380,000 $ 600,000
d. $800,000 $ 600,000
25. Assuming that the completed contract method is used, compute the amount of gross profit (loss) to be recognized in 2012 and 2013, respectively.
a. $50,000 and 60,000.
b. $0 and 60,000.
c. $50,000 and 300,000.
d. $0 and $0.
26. If in 2013, the estimated cost to complete is estimated to be 400,000, instead of 300,000, compute the gross profit (loss) recognized in 2013 for the percentage-of-completion method and the completed contract method, respectively
a. $(20,000) and 0.
b. $0 and (20,000).
c. $(20,000) and (20,000).
d. $0 and $0.
Step by Step Solution
3.49 Rating (152 Votes )
There are 3 Steps involved in it
Step: 1
Answer Number 22 2012 2013 2014 Contract Value A 1200000 1200000 1200000 Cost incurred during the ye...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started