Information for Garner Company's direct-labor costs for the month of September 2005 was as follows: Actual direct-labor hours: Actual direct-labor hours 34,500 hours Standard direct-labor
Information for Garner Company's direct-labor costs for the month of September 2005 was as follows: Actual direct-labor hours:
Actual direct-labor hours | 34,500 hours |
---|---|
Standard direct-labor hours | 35,000 hours |
Total direct-labor payroll | $241,500 |
Direct-labor efficiency variance |