Question
Information for the Time-Cost Model Exercise Task Immediate Predecessors Normal Time (weeks) Crash Time (weeks) Normal Cost Crash Cost Crash cost per week A NONE
Information for the Time-Cost Model Exercise | ||||||
Task | Immediate Predecessors | Normal Time (weeks) | Crash Time (weeks) | Normal Cost | Crash Cost | Crash cost per week |
A | NONE | 4 | 3 | $5,000 | $13,000 | $8,000 |
B | A | 6 | 4 | $10,000 | $20,000 | $5,000 |
C | A | 7 | 7 | $6,000 | $6,000 | |
D | C | 8 | 6 | $4,000 | $8,000 | $2,000 |
E | B & C | 9 | 7 | $4,000 | $9,000 | $2,500 |
F | D & E | 5 | 4 | $5,000 | $9,000 | $4,000 |
G | F | 4 | 3 | $3,000 | $6,000 | $3,000 |
Your firm needs to find a new supplier for a key raw material. The table below lists the steps that need to be complete. Due to unforeseen issues, you need to expedite the project in order to continue to supply your customers with the finished product you are producing with this key raw material. What is the length of the critical path (before crashing)?
Your firm needs to find a new supplier for a key raw material. The table below lists the steps that need to be complete. Due to unforeseen issues, you need to expedite the project in order to continue to supply your customers with the finished product you are producing with this key raw material. What is the first activity that should be crashed?
Your firm needs to find a new supplier for a key raw material. The table below lists the steps that need to be complete. Due to unforeseen issues, you need to expedite the project in order to continue to supply your customers with the finished product you are producing with this key raw material. What is the total cost of crashing?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started