Question
1 Approved Answer
Information for two competing-investment projects are given as: n Truck A Truck B 0 -$10,000 -$35,000 1 11,000 20,000 2 11,000 20.000 3 [10.000 Compute
Information for two competing-investment projects are given as: n Truck A Truck B 0 -$10,000 -$35,000 1 11,000 20,000 2 11,000 20.000 3 [10.000 Compute the net present worth difference between two trucks using an infinite planning horizon with project repeatability. Assume MARR=8%. a) None of the answers are correct b) Between $19,176 and $20,367 c) Between $29,176 and $30,367 d) Between $23,176 and $24,367 e) Between $17,176 and $18,367 f) Between $25,176 and $26,367