Information on a projects activities is shown in the following table: Activity Immediate Predecessor Activity Time (wks) Total Budgeted Cost A - 5 25,000 B
- Information on a projects activities is shown in the following table:
Activity | Immediate Predecessor | Activity Time (wks) | Total Budgeted Cost |
A | - | 5 | 25,000 |
B | - | 3 | 27,000 |
C | B | 2 | 14,000 |
D | A | 8 | 48,000 |
E | D | 3 | 36,000 |
F | C, E | 4 | 60,000 |
G | C, E | 6 | 30,000 |
H | F | 6 | 36,000 |
I | G | 5 | 20,000 |
J | G, H | 3 | 30,000 |
K | I | 2 | 40,000 |
L | J | 3 | 21,000 |
- Create a Gantt chart based on earliest start times. (20 pts)
- Create a budget cost chart, using earliest start times. (20 pts)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started