InformationTechnology Project Managem Scenario: * Suppose you just signed a contract with a consulting firm called Dr. Petes Consulting for developing an IS. *Project Budget,
InformationTechnology Project Managem Scenario:
* Suppose you just signed a contract with a consulting firm called Dr. Petes Consulting for developing an IS.
*Project Budget, Schedule, Tasks:
# $10,000
# 3 months
# 10 Tasks
- $1,000 per task
- 4 tasks 1st month
- 3 tasks 2nd month
- 3 tasks 3rd month
At the end of Month 1, you receive the following invoice:
Invoice
Dr. Petes Consulting
Amount Due: $5,000
Payment Due: Immediately
Work Completed for Month 1
Task 1: $2,000
Task 2: $1,000
Task 3: $2,000
Questions to answer:
1.How is the project doing regarding budget and schedule?
2.What is the estimate at completion (EAC) assuming variances encountered will likely continue for the remainder of the project?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started