Question

1 Approved Answer

INITIAL BUDGET INFORMATIONOur initial plan was to make and sell 5 0 0 wrenches. We budgeted 2 lbs . of steel for each wrench,and expected

INITIAL BUDGET INFORMATIONOur initial plan was to make and sell 500 wrenches. We budgeted 2 lbs. of steel for each wrench,and expected to pay $1.50 per pound for the steel. We budgeted $20 per hour for labor, and expected it to take3 hours to make each tool. Our initial plan was to sell the 500 wrenches for $120 each.We budgeted $8000 for insurance (fixed overhead), and we decided to use labor hours as the driver forallocating utilities costs (variable overhead). We expected to have $12,000 in utilities costs.FLEXIBLE BUDGETPrepared after-the-fact, using actual quantity of sales, and the Variable OH Application rate determined with Master Budget.
ACTUAL RESULTS(1) We receive an order for 550 units at $125.00 each(2) We purchase 1,400 lbs. of materials., paying 1,960.00, or $1.40 per lb.(3) We drawdown 1250 lbs. materials to produce 550 wrenches .(4) We drawdown (pay) $21.00 hr. for 1640 hours of labor to produce the 550 wrenches.(5) We incur variable overhead expenses (ex.- utilities) of $11,890.00.(6) Fixed overhead (insurance)costs are $7,800. Fixed overhead is deemed to be a period expense.(7) We sell all 550 units at $125 each.
PART TWO: For Part Two of this problem, you are required to complete an analysis of variance, breaking Total Variance into its various elements,which are identified on the provided (two) variance worksheets,
SPENDING (OR "COST") VARIANCES CALCULATION SHEET
GENERALIZED MODEL FOR ALL VARIABLE COST VARIANCES (Mtls, Labor, Var. OH)
(1)
(2)
(3)
Actual Qty of Input
Actual Qty of Input
Standard Qty of Input
at Actual Price:
at Standard Price:
at Standard Price:
(AQ x AP)
(AQ x SP)
(SQ x SP)
Note: Numbers appearing below in parenthesis refer to above boxes.
Combined Spending (or "Cost") Variance
(1)-(3)
Price Variance Portion
Quantity Variance Portion
(1)-(2)
(2)-(3)
Materials
Price Variance Portion
Quantity Variance Portion
(1)-(2)
(2)-(3)
(AQ x AP)-(AQ x SP)=(AP - SP)(AQ)
(AQ x SP)-(SQ x SR)=(AQ - SQ)(SP)
(AP - SP)(AQ)
(AQ - SQ)(SP)
Labor
Price ("Rate") Variance
Quantity ("Efficiency") Variance
(1)-(2)
(2)-(3)
(AH x AR)-(AH x SR)=(AR - SR)(AH)
(AH x SR)-(SH x SR)=(AH - SH)(SR)
(AR - SR)(AH)
(AH - SH)(SR)
Variable Overhead (assuming Labor Hours is Driver)
Price ("Spending")Variance
Quantity ("Efficiency") Variance
(1)-(2)
(2)-(3)
(AH x AR)-(AH x SR)=(AR - SR)(AH)
(AH x SR)-(SH x SR)=(AH - SH)(SR)
(AR - SR)(AH)
(AH - SH)(SR)
Note: This formulation for overhead variances may differ from textbook
formulas, but resulting answers are identical. Take your pick!
Also, remember the hours and rates relate to the OH driver!
FIXED COSTS OVERHEAD VARIANCE
We do one variance for fixed costs overhead: the Spending Variance, which
is the difference between the planned costs and actual costs.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3