Instructions: Complete the MPS table 10 11 12 12 25 25 15 0 Period On- 1 2 3 4 5 6 7 8 6
Instructions: Complete the MPS table 10 11 12 12 25 25 15 0 Period On- 1 2 3 4 5 6 7 8 6 Hand Forecast 25 25 25 25 0 15 35 25 30 20 20 Customer Orders 20 30 15 10 11 0 0 20 20 25 0 0 Projected 25 Available Available to Promise MPS MPS Lot Size = 50 Lead-time=0 30 30 0 Projected Available = BI+MPS-Max (Customer Orders; Forecast) ATP action bucket = BI + MPS - customer orders between current MPS and next scheduled replenishment Available to Promise = MPS - customer orders between current MPS and next scheduled replenishment Questions: -Would you accept an order for 25 units in period 6? Why? (answer in complete sentences) -Would you accept an order for 50 units in period 8? Why? What could you do instead? (answer in complete sentences)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started