Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

ion 1 Activity A is worth $300, is 100% complete, and cost $350. Activity B is worth $100, is 95% complete and costs $85 et

image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed
image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed
ion 1 Activity A is worth $300, is 100% complete, and cost $350. Activity B is worth $100, is 95% complete and costs $85 et so far. Activity C is worth $200, is 75% complete, and has cost $175 so far. The total budget is $1500. What is the ered cost variance? ed out of O a. $500.00 ag question O b. $55.00 O c. $-45.00 O d. $-65.00 Clear my choice3 You are managing the project when you discover an estimated completion date will occur after the desired date. What should you do FIRST? ed out of O a. Negotiate for more time O b. Explain to the customer that the project cannot be done on time g question O c. Add resources to the project O d. Evaluate the possibility of doing more activities in parallelQuestion 4 In Access, which of the following statements about 'Reports' is false? Not yet answered O a. Reports is an object in a database which is used for producing well formatted reports. Marked out of 1.00 b. Reports do not allows us to create sub-total and total fields Flag question O c. In MS Access, you can have a number of pre-formatted Reports, Old. Formatting in Reports in MS Access may include the filters, datatypes, data-range, corporate information - both static and dynamic - such as logo, address, date, report number etc. Clear my choiceJestion 2 In situations where the Databases are controlled by different systems, the data integration can not be achieved pt yet through: swered larked out of O a. Developing an API (Application Programming Interface) 100 O b. Data parsing Flag question O c. Use of Middleware d. Data Tunneling Clear my choiceon 6 You want to maintain qualifications of your human resources in MS Project. You best option will be: et vered a. Enter these in Notes ked out of O b. It is not possible to enter qualifications of resources in MS Project O c. Create a database of resources in an excel file. Flag question O d. Enter these Project Information file Clear my choice7 A project has three critical paths. How does this affect the project? d O a. It makes it easier to manage. out of O b. It requires more people. O c. It increases the project risk. question O d. It makes it more expensive. Clear my choiceIn attempting to complete the project faster, the project manager looks at the cost associated with crashing each activity. The BEST approach to crashing would also include looking at the: O a. Risk impact of crashing each activity. O b. Customer's opinion of what activities to crash. O c. Project phase the activity is due to occur in. O d. Boss's opinion of what activities to crash and in which order. Clear my choice3 Which of the following is incorrect about Cost Resources in MS Project? O a. Cost of this cost will be calculated by MS Project as Duration multiplied by cost. ut of O b. The currency value of cost resources does not depend on the amount of work don O c. Cost resources do not have a calendar uestion O d. Cost resources are created as a type of resource and then assigned to a taskon 8 After analyzing the status of your project, you determine that the project is two weeks behind schedule. You wa at to recover the original schedule if possible, and there is plenty of remaining budget in the current plan. What is ered the BEST option? ed out of O a. Compress the testing and quality management portion of the project lag question O b. Inform the team that overtime will be required for a short time to recover the schedule O c. Reduce the scope of work with a change request O d. Crash the schedule Clear my choice15 The sponsor of the project you are managing asks you to compress the duration of the project. Which of the following is correct? out of a. Crashing always shortens the timeline but often increases risk. Ob. Fast tracking often results in rework and crashing often results in increased cost. question c. Fast tracking will result in less parallel activities than crashing the project. d. Crashing is only a viable alternative if earned value analysis indicates that the project is ahead of sche and under budget.Due 2022 16 A Work Package contract has been signed with an Earning Rule of 30/70. This is a $100,000 work contract. The project is 80% complete. For this Work Package, the project will show as having earned a value of: d out of O a. $30,000 O b. $20,000 question O c. $80,000 O d. $70,000 Nextestion 14 You are using MS Project for your project. How many type of rates you can assign to any resource? t yet swered O a. Two arked out of O b. Four O c. One Flag question O d. FiveWhich of the following statements is not true, based upon your class lessons? O a. Access can import data from a worksheet in excel file O b. Access can not import data from a named range in an excel file O c. Access can import data from a named range in an excel file O d. Access can import data from a named range or a worksheet in excel file Log Major Assignment Jump to...17 You have a project to build a new fence. The fence has four sides. Each side is to take one day to build and it is budgeted at $1.000 per side. Today is the end of day three. At this point in time, side 1 has been completed at a cost of $1,000, side 2 has been completed at a cost of $900K, side 3 is 50% complete and $1,000 is spent, side 4 is out of 75% complete at a cost of $300. At the end of Day 3: question Qa. The project is behind schedule O b. None of the above O c. The project is progressing according to schedule Od. The project is ahead of schedule Clear my choiceWhich of the following statements is not true, based upon your class lessons? O a. Access can import data from a worksheet in excel file O b. Access can not import data from a named range in an excel file Qc. Access can import data from a named range in an excel file O d. Access can import data from a named range or a worksheet in excel file Clear my choice Log Major Assignment Jump to

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitality Law Managing Legal Issues In The Hospitality Industry

Authors: David K Hayes, Stephen C Barth

3rd Edition

047008376X, 9780470083765

More Books

Students also viewed these General Management questions