It cost a contractor $9,765 to manufacture their first unit. the company expects to experience a 75% unit learning curve. Estimate the cost of the
It cost a contractor $9,765 to manufacture their first unit. the company expects to experience a 75% unit learning curve. Estimate the cost of the 15th unit.
- $3174
- $3090
- $4287
- $4120