It is August 1 , 2 0 1 9 ? ? and work on Project ABC is beginning to ramp up . The site is

It is August 1,2019?? and work on Project ABC is beginning to ramp up. The site is currently operating as a parking lot while the project managers are working on the design of the project, which is zoned as a 12-floor tower consisting of rental
units.
The parking lot is averaging $36,000/month in net revenues. Although the lot will be closed in October for repaving, management expects revenues to remain consistent for the rest of 2019, including when the lot reopens in November for
the annual Christmas market. Repaving the lot is expected to cost around $17,000 and cannot be avoided as one section of the lot is starting to have large potholes. New lights for the lot will also be installed at the end of October for $10,000,
to increase visibility for the customers. All other expenses for the lot have been consistent on a month to month basis.
The executives have been quite content with the management company that has been operating the parking lot, although they charge fees for operating the parking machines at $3,000 month, in addition to their management fee of 10% of net
revenues. With the current contract set to expire in September, the|executives are about to approve the proposed contract extension even though the management fee will increase by an additional 2% per month, starting October 1,
Pre-development costs for design work on the project for the remainder of the year are expected to average $19,000/month for August to October, $46,000 for November, and only $5,000 for December due to the holidays.
Financial results for the year up to July 31,2019?? are as follows:
Project ABC
For the seven months ending July 31,2019
The Controller has asked you to prepare a summary for the executives, who have asked if any additional cash is required to be injected into the project and when it will be required. All cash for operating revenues and expenses are collected/paid in the subsequent month. All other capital and pre-development costs are paid in the month that they are incurred. Cash contributions occur on the 5th of every month and the executives prefer to inject as little cash as possible
into the project.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions