It is currently day 29 of a project. BCWS, BCWP, and AC to date are 13m, 15m, and 11m respectively. Then what is the SPI
It is currently day 29 of a project. BCWS, BCWP, and AC to date are 13m, 15m, and 11m respectively. Then what is the SPI of the project to date? (Please keep two decimal points!)