It is proposed to increase the capacity of the existing water transmission line in a certain city. Among the options are as follows: Option 1:
It is proposed to increase the capacity of the existing water transmission line in a certain city. Among the options are as follows:
Option 1: constructing a parallel pipe.
The initial cost for this proposed option is Php 2, 500, 000 with a life of 20 years and the annual operating cost is worth Php 50, 000
Option 2: constructing a booster pumping station
This costs Php 1, 000, 000 with a life of 20 years. A pumping equipment which costs Php 200, 000 with a life of 10 years and a scrap value of Php 20, 000 is also included in this option. The annual operating cost is Php 150, 000.
For both options, money is worth 12%.
Using the present value method, what is the present value of option 1?
A. Php 2, 250, 000
B. Php 2, 050, 000
C. Php 1, 870, 000
What is the present value of option 2?
A. Php 2, 580, 000
B. Php 2, 080, 000
C. Php 2, 380, 000
Which option is more economical?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started