It is the end of the 4th month of an 18 months project. The total project cost is $3,623,400. 60% of the planned work has
It is the end of the 4th month of an 18 months project. The total project cost is $3,623,400. 60% of the planned work has spent, and 39.9% of the planned budget has completed. Please round all ratio values to the two decimal places and round all dollar values to the nearest dollar. For a negative number, use a dash in front of the number. PV is ? EV is ? AC is ? CPI is ? EAC is