An assembly line with 18 tasks is to be balanced. The longest task is 2.6 minutes, and the total time for all tasks is 14 minutes. The line will operate for 457 minutes per day.
a. What are the minimum and maximum cycle times? (Round your answers to 1 decimal place.)
b. What range of output is theoretically possible for the line? (Round your answers to whole numbers.)
c. What is the minimum number of workstations needed if the maximum output rate is to be sought? (Round your answer up to a whole number.)
d. What cycle time will provide an output rate of 123 units per day? (Round your answer to 1 decimal place.)
e. What output potential will result for the following cycle times? (Round your answers to whole numbers.)
PrevQuestion 3 of 10 Total3 of 10Visit question mapNext\\

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Management

Authors: Robbins, DeCenzo, Coulter

7th Edition

132996855, 0-13-610982-9 , 9780132996853, 978-0-13-61098, 978-0136109822

More Books

Students also viewed these General Management questions