Item 8 Item 8 Olmo, Inc., manufactures and sells two products: Product K0 and Product H9. The annual production and sales of Product of K0

Item 8

Item 8

Olmo, Inc., manufactures and sells two products: Product K0 and Product H9. The annual production and sales of Product of K0 is 1,000 units and of Product H9 is 1,000 units. The company has an activity-based costing system with the following activity cost pools, activity measures, and expected activity:

Activity Cost Pools Activity Measures Estimated Overhead Cost Expected Activity
Product K0 Product H9 Total
Labor-related DLHs $ 549,408 10,000 5,000 15,000
Production orders orders 52,419 1,100 200 1,300
Order size MHs 835,016 2,800 3,200 6,000
$ 1,436,843

The overhead applied to each unit of Product K0 under activity-based costing is closest to:

Vanvalkenburg, Inc., manufactures and sells two products: Product Q5 and Product J0. The company has an activity-based costing system with the following activity cost pools, activity measures, and expected activity:

Estimated Expected Activity
Activity Cost Pools Activity Measures Overhead Cost Product Q5 Product J0 Total
Labor-related DLHs $ 191,748 3,000 2,800 5,800
Production orders orders 70,536 300 500 800
Order size MHs 295,592 4,300 4,500 8,800
$ 557,876

Forner, Inc., manufactures and sells two products: Product Z1 and Product Z8. The company has an activity-based costing system with the following activity cost pools, activity measures, and expected activity:

Estimated Expected Activity
Activity Cost Pools Activity Measures Overhead Cost Product Z1 Product Z8 Total
Labor-related DLHs $ 112,190 600 2,000 2,600
Machine setups setups 40,440 500 700 1,200
Order size MHs 609,770 3,000 3,200 6,200
$ 762,400

The activity rate for the Machine Setups activity cost pool under activity-based costing is closest to:

The activity rate for the Production Orders activity cost pool under activity-based costing is closest to:

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting For Construction Frameworks Productivity Cost And Performance

Authors: Rick Best, Jim Meikle

1st Edition

1138293970, 978-1138293977

More Books

Students also viewed these Accounting questions