Item iPhone LS: L4L LT: 2 Period 1 2 3 4 5 Gross Requirements 40 20 35 50 36 Scheduled Receipts 30 Projected on Hand
Item | iPhone | ||||||
LS: L4L | LT: 2 | Period | 1 | 2 | 3 | 4 | 5 |
Gross Requirements | 40 | 20 | 35 | 50 | 36 | ||
Scheduled Receipts | 30 | ||||||
Projected on Hand | 40 | ||||||
Net requirements | |||||||
Planned Order Receipts | |||||||
Planned Order Releases |
In the above MRP matrix, what is the planned order release for iPhone in period 3?