Question

1 Approved Answer

Item2 5points eBook Print Check my workCheck My Work button is now enabled2 Item 2 The following table lists the components needed to assemble an

Item2

5points

eBook

Print

Check my workCheck My Work button is now enabled2

Item 2

The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand.

Item Lead Time Amount on Hand Direct Components
End 2 0 L(2), C(1), K(3)
L 2 11 B(2), J(3)
C 3 15 G(2), B(2)
K 3 20 H(4), B(2)
B 2 25
J 3 34
G 3 3
H 2 0

Click here for the Excel Data File

a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You dont need to develop an MRP plan.)

b. An order for the end item is scheduled to be shipped at the start of week 11. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You dont need to develop an MRP plan.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

43 Ways To Finance Your Feature Film A Comprehensive Analysis Of Film Finance

Authors: John W. Cones

3rd Edition

0809326930, 978-0809326938

More Books

Students also viewed these Finance questions