itonHi I need help with this ques ABC Corporation uses an activity-based costing system with three activity cost pools. The company has provided the following
itonHi I need help with this ques
ABC Corporation uses an activity-based costing system with three activity cost pools. The company has provided the following data concerning its costs and its activity based costing system:
Costs:Wages and salaries$269,000Depreciation214,000Utilities192,000Total$675,000
Distribution of resource consumption:Activity Cost Pools
AssemblySetting upOtherTotalWages and salaries45%25%30%100%Depreciation30%20%50%100%Utilities20%50%30%100%
How much cost, in total, would be allocated in the first-stage allocation to the Assembly activity cost pool?
$303,750
$135,000
$210,983
$223,650
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started